Step 5 of 6
Coordinated Process
Fulfillment & Installation
End-to-end project coordination from manufacturing to installation completion
12-16 wks
Delivery Time
Estimated delivery window
2-3 wks
Installation
Installation duration
Active
Coordination
Project management status
Real-time
Tracking
Visibility level
Project Timeline - Quote AW-2024-1609
MAGNETOM Vida 3T MRI System - Wake Forest Baptist Medical Center
Order Processing
3 days
Complete
Manufacturing order placement and scheduling
Completed: 1/17/2024
Manufacturing
12 weeks
In Progress
Equipment manufacturing and quality testing
Started: 1/18/2024 • Est. completion: 4/14/2024
Progress25%
3
Pre-delivery Inspection
1 week
Pending
Final quality check and documentation
Est. start: 4/9/2024
4
Logistics Coordination
2 weeks
Pending
Shipping and delivery scheduling
Est. start: 4/14/2024
5
Site Installation
3 weeks
Pending
On-site installation and commissioning
Est. start: 4/30/2024
6
Training & Handover
1 week
Pending
User training and project completion
Est. start: 5/21/2024
Customer Information
Project delivery details and contacts
Delivery Location
Wake Forest Baptist Medical Center
Medical Center Blvd, Winston-Salem, NC 27157
Primary Contact
Sarah Johnson
Radiology
+1 (336) 716-2011
sarah.johnson@wakehealth.edu
Key Dates
Manufacturing Complete:4/14/2024
Delivery Window:2024-05-01 - 2024-05-03
Installation Start:5/5/2024
Project Completion:5/28/2024
Project Team
Dedicated team members and their responsibilities
Project Manager
Active
Jennifer Adams
j.adams@alfredworkflow.com
+1 (555) 123-4567
Responsibilities:
- Overall project coordination
- Timeline management
- Stakeholder communication
Installation Coordinator
Active
Mike Rodriguez
m.rodriguez@alfredworkflow.com
+1 (555) 234-5678
Responsibilities:
- Site preparation
- Installation scheduling
- Technical coordination
Customer Success Manager
Active
Sarah Chen
s.chen@alfredworkflow.com
+1 (555) 345-6789
Responsibilities:
- Customer communication
- Training coordination
- Support handover
Real-time Tracking & Communication
Live updates and stakeholder notifications
Manufacturing Status
MAGNETOM Vida 3T
In Production
Serial Number: MV3T-2024-0847
Production Line: Erlangen, Germany
Est. Completion: April 15, 2024
25% Complete
Logistics Planning
Shipping Coordination
Planning
Route: Erlangen → Winston-Salem
Transport: Specialized Medical Equipment
Est. Transit: 5-7 days